Sidewalk Project in Tanjung Priok Has Touched 60 Percent

Total length of the sidewalk is about 1.6 kilometers by spending Rp 7 billion

The arrangement and development of the sidewalks in Tanjung Priok area, North Jakarta has reached 60 percent. It is targeted to be completed in early December 2017.

Section Head of Road Infrastructure and Utility Network Completeness, Libertus Sagala stated the sidewalk arrangement on Jalan Enggano has 1.3 kilometers length and 300 meters length on Jalan Yos Sudarso. Both are interconnected with each other. 

Sidewalk Arrangement on Jl. Sudirman-MH Thamrin Launched

"Sidewalk arrangement in Tanjung Priok Sub-district has reached 60 percent. Total length of the sidewalk is about 1.6 kilometers by spending Rp 7 billion," he stated, Monday (10/9).

It will be equipped with the guiding block and the utility block. Additionally, there will be bollards along the sidewalk. Then for its surface will use floor hardener.

He added those utility installation will use drilling method through ducting box that is installed with a distance every 25 meters. Box ducting itself has 2.5 meters depth with 2 meters length.

Linked News
Popular News indeks
  1. Public Urged to Use Public Transit for GBK Events to Avoid Heavy Traffic

    access_time05-06-2026 remove_red_eye1313 personAldi Geri Lumban Tobing
  2. Traffic Measures Prepared to Ease Congestion Around GBK This Weekend

    access_time04-06-2026 remove_red_eye1227 personAldi Geri Lumban Tobing
  3. Central Jakarta Government Responds Quickly to Fire Victims in Tanah Tinggi

    access_time04-06-2026 remove_red_eye1037 personFolmer
  4. Pramono Launches Jumbo Biopores, Aims for Jakarta Waste Management Blueprint

    access_time07-06-2026 remove_red_eye968 personDessy Suciati
  5. Pram Inaugurates Matraman Health Center, Calls for Seamless Public Service

    access_time05-06-2026 remove_red_eye799 personDessy Suciati